A program manager reviews a Claude-drafted board update. The executive summary says all milestones are on track, but the milestone table later in the document shows two milestones as delayed. What is the most appropriate action?

Show answer and explanation

Answer: A — Check both statements against the project tracker and correct whichever part is wrong before sending

An internal inconsistency means at least one part is wrong. The fix is to check both against the system of record and correct the output (a). Deleting the table hides the conflict instead of resolving it, and may remove the accurate part (b). Picking the summary without checking is a guess (c). A new version that happens to be consistent could be consistently wrong (d).