CCAR-P practice › Stakeholder Communication & Lifecycle Management · Question 101 of 110
Stakeholder Communication & Lifecycle Management
After launch, an engineer edited the production prompt to make a document assistant's tone warmer. A week later, finance notices that extracted invoice dates are wrong more often. Which missing lifecycle mechanism best explains how this reached production?
Show answer and explanation
Answer: B — Gated change control, where every prompt change passes the regression eval before release, with rollback
(b) is right: iteration must run through change control; a regression eval covering extraction would have caught the drop before release, and rollback would limit the damage. (a) buys capability instead of process. (c) and (d) help communication and understanding but wouldn't have stopped an unevaluated change.
Keep going
More Stakeholder Communication & Lifecycle Management questions
- Your production system is pinned to a model version, and the provider announces that…
- A retail bank's VP of operations asks you for 'an agent that handles card disputes end…
- A feasibility probe for invoice extraction scored very well on 30 invoices the finance…
- You are running discovery for an assistant that will answer employees' leave and…
- A claims-triage system routes drafts to adjusters. Product wants to stop human review…