A build team is about to hand a Claude-based underwriting assistant to the platform operations team. Which condition best shows the handoff is ready?

Show answer and explanation

Answer: D — The ops team has run the eval suite, shipped a change through the pipeline, drilled a runbook and has access

(d) is right: handoff is complete when the new owner can verify, change and fix the system without the build team, demonstrated against explicit exit criteria. (a) and (b) transfer material, not capability. (c) shows the system was stable while someone else operated it, not that the new owner can run it.