CCAO-F practice › Output Evaluation and Validation · Question 35 of 100
Output Evaluation and Validation · Select TWO
A program manager asks Claude to turn a verified, detailed project status report into a version for the executive steering committee, which has ten minutes to review it. Select the two most appropriate instructions to include.
Show answer and explanation
Answer: A and C — Lead with the decision needed from the committee and the single biggest risk / Keep all figures, dates, and commitments exactly as in the verified report
For a time-pressed executive audience, put the most important information first (a). Editing for an audience must not change verified facts (c). Including every task-level detail (b) or making it long to look thorough (d) works against a ten-minute review, and more detail doesn't mean a better output.
Keep going
More Output Evaluation and Validation questions
- A marketing lead uploads a quarterly campaign spreadsheet and asks Claude for a one-page…
- A project manager pastes meeting notes into a chat and asks Claude for a summary listing…
- A consultant receives a market-sizing estimate from Claude with several precise figures…
- An operations analyst has 15 minutes to review Claude's summary of a supplier's 30-page…
- A teacher uses Claude for several tasks this week. Which output most warrants checking…